Produce assembly in onther Location

former_member182449
Participant
0 Kudos

Dear Expert,

I need your Help regarding to this issue :

I have Product P-200 for location 1000 (Location type 1001) , and Valid PPM with Input Product R-200

This Product R-200 is assembly and have PPM in Different Location 1100 (Location Type1001)

When I run Heuristics in SNP , I can't find Dependent Requirement for this item in this Product Location R-200 - 1100 Based on Demand for Product Location P-200 1000

Could you Please help mr how i can implement this scenario

Kindly Regards

Rami

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member182449
Participant
0 Kudos

UN

Former Member
0 Kudos

Hi,

1. The product R-200 in loc 1000 should be defined as ext proc ( Proc type F).

2. The same product should be defined as in house production in loc 1100.

3.A Transportation lane should exist from 1100 to 1000 for this product.

4.Then take Heuristic run.

5. Dep reqmts will generate.

Or refer notes 619898

Thanks,

nandha

Edited by: S.Nandakumar on Oct 12, 2010 7:06 AM

former_member182449
Participant
0 Kudos

hi,

Appreciate your effort

I did as you said exactly except Transportation Lane , but brfore Transportation lane i found dependent Requirement in Product Location R-200 1000

After i create Transportation lane i found Requirement Generated in Distribution Demand (Planned) for Product

Location R-200 1100

and Also still found dependent Requirement in Product Location R-200 1000

Please Advise

Regards

Rami

Former Member
0 Kudos

Hi,

1.Delete all the dep reqmts and take Heuristic run for FG separately.

2.Take another heuristic run for component.

Thanks,

nandha

former_member182449
Participant
0 Kudos

Hi ,

This not solve the issue

Please Advise

Rami

Former Member
0 Kudos

Hi Rami

The Dependant Requirement for R200 1000 should have (after the heuristic run) a receipt item for it (generally a Purchase Requisition) from source location 1100. This Preq is the item that should now be generating your Distribution Demand (planned) for R200 1100. The requirement in 1000 remains but the transportation lane now places this required demand on the location 1100 where your PPM exists for the product R200.

Within location 1100 you will now need to run the Location Heuristics to generate the BOM explosion for the PPM for your product to create a receipt element in Location 1100.

Hope that helps

Ian

former_member182449
Participant
0 Kudos

Dear Jan ,

Thanks a lot

Regards

Rami