on 10-11-2010 1:27 PM
Hi Experts,
Here I really struggling with source of supply determination for APO type of scheduling agreements. In my case for OLTP type scheduling agreements, source of supply is getting determined but not for APO type. I have maintained required master data(LP type and ext planning indicator 1) in ECC. Please give your inputs this is very critical situation.
Thanks,
Shirish
Are the transportation lanes in APO maintained properly?
Aban