hi,
We are implementing Service procurement in SRM 5.5 server. We are also go for SUS. Is there any issues like service procurement specific scenario not works for classic or extended classic scenario.
Because based on that decision we are planning for SUS-MM or SUS-EBP scenario.
Some one throws some light on this. Thanks in advance.
Sen
Hi Senthilvel,
They are some limitations for the extended classic scenario (GR and IV).
Please read the following oss notes :
543544 : ecs limitations
868192 : mm sus services limitations
Kind regards,
Yann