Plan Monitor - Key Figure for Resources

Former Member
0 Kudos

Hi Gurus,

I have a doubt related to the plan monitor.

We decide to configure the plan monitor and some key figures for the resources.

We are using the key figures: Resource Setup Time and Resource Load, but when we run the plan monitor for 2 resources in the selection for example, the result is the summe of the resources.

For the Resource Setup Time is possible to display single results of each resource, but for the resource load is not possible to "Display Singe Results" it always shows the load as a summe of all resources.

Is that right? Is not possible to show the results by resource of the "Resource Load"?

Thanks in advance

Thiago Cyrillo

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Have you tried in tcode /SAPAPO/PMON -go to key figure schema and select display single results. It is possible to dispay resource wise resource load in plan monitor.

Also make sure that in key fighre schema definition you have checked check box- Display of individual records and default as display and not do not display.

Regards,

Santosh

Former Member
0 Kudos

Hi Santosh thanks for the answer.

I have forgotten the flag "Display of individual results".

Now I can see the individual resources.

Regards

Thiago Cyrillo