I'm new in PS, is it posible to auto generate /create Service Order from WBS / Network-activty ?
if yes, can you give step by step .
Thanks
Hi,
You cant auto-generate service order from PS. But you can assign created service order to WBS or activity thru its Additional data tab. If you assign to WBS order costs flow to WBS whereas if you assign to activity you can schedule the service order along with activity.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You cannot create PM order directly from project/ WBS element. If your requirement is for pre-investing then you can use IM (investment managemnt) appropriate request to generate PM order.
You can use on other hand PM order linkage with PS for scheduling or budget controlling point of view.
However if you wish to create PM order then use BAPI to create it from project on certain change of WBS element status through development.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Callia Raissa,
... is it posible to auto generate /create Service Order from WBS / Network-activty ?
Yes. You can create service PR & then with reference to that PR, you can create PO.
if yes, can you give step by step
Please read [SAP Help|http://help.sap.com/saphelp_47x200/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm] .
And also search the forum.
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.