on 10-07-2010 10:00 AM
Hi Team,
My scenario is as below:
I have created two logical components:
ZLC1: SL1:200 (DEV)->SL1:300(QA)---->SL1:400(PRD)
ZLC2:SL1:210(DEV)->SL1:300(QA)--->SL1:400(PRD)
All the above five clietns are created within a single system (System ID:SL1, Solution Manager System) to activate ChaRM.
SDCR and SDHF is working fine.
Requirement is:
When i execute the action "Set-in Development" at first time, it is giving me the pop-up to select the development system as per the logical component. First time i have selected 200 client. I have create the transport & released the transport. Now would like to create one more transport request in another development client (210 client). I was under the uderstanding that, when i execute the action "Create Transport Request", system will give me a pop-up to selec the development client. But system by default takes me to the earlier development client (200).
How to change this default selection of the client login?
Note: The functional requirement is, all the custimizing to be done in 200 client and all ABAP developments to be done in 210 client. So i need this option.
Your guidance required.
Thanks
PSK
not solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Do you use an urgt correction ? I'm quite sure that an urgt correction cannot have multiple source systems... In that case you will have to create a normal correction.
BR.
Stéphane.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.