on 10-07-2010 6:59 AM
Dear All
I have a scenario project triggered from sales order. When my sales order saved my project get triggered in background and my planned revenue from sales order automatically flow in project report. Up till now I donu2019t have any issue.
Now my client required milestone billing activate in system. I have done necessary configuration to activate milestone billing and also maintain revenue element for billing plan in planning profile with element type 11. When I create milestone for activity and maintain invoicing percentage its copy to my billing plan in sales order but now my planned revenue not flow in report.
Please let me know any specific option which I have missed out.
Regards
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.