on 10-06-2010 3:34 PM
Dear All,
When using CO46 for a sales order it does everything correct exept for a specific material. It is displayed above the sales order in the hierarchy, like if it is not contained in it and there is no exploded view possible.
When I look closer to the MRP for the material it has planned orders but the orders reducing quantity don't link to the sales order. The MRP element data is empty.
Anybody has a clue?
Thanks in advance,
Michaë
The material in the SOI created collective requirements. Change Material Master availability check to 02 and recreate SOI