on 10-06-2010 6:35 AM
Hi Gurus,
In our scenario, we are using bottom-up scheduling method and the Scheduling type as "Forwards". I have given the Project Start date and maintained relationship for all the acitivites along with duration. First time when I scheduled I got the Basic finish dates for Project and the WBS elements. According to this, I presume that whenever there is a change in the duration of any activity and a scheduling is carried out, the finish dates of the all the WBS elements and the Project definition gets changed whereas it is not automatically getting updated. Only if I remove the existing finish dates (which got populated during my first scheduling) and schedule, it is refreshing the dates. Where I am making the mistake ?
Awaiting your expert guidance.
Thanks in advance,
Vinodh
Hi,
Try ticking the "Adjust Basic Dates" option in the Control Parameters for WBS Scheduling (SPRO) and revert.
Regards,
Gokul
Edited by: Gokul on Oct 6, 2010 11:54 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
-deleted-
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vinodh,
This option doesnt work for the forward scheduling, this will work for the back ward scheduling only. In OPU6 transaction press F1 in the fields adjust dates and read the help document, which explains in detail.
Also, you have to enable the option Adjust dates in for the WBS element scheduling, follow the path: IMG-PS-Dates-Date planning in WBS - Define parameters for WBS scheduling. Here also choose the scheduling method as Network determines dates
I think by selecting the option Automatic Scheduling, the dates are automatically updated when ever you carry out any changes in the dates and save, means no need to carry the scheduling again.
Try the above and revert with your observations.
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This option doesnt work for the forward scheduling, this will work for the back ward scheduling only
I dont see in F1 help document for "Adjust Dates" field saying that it wont work for Forward scheduling type. It clearly says that for forward scheduling "Basic Finish Dates" will be adjusted.
Ahmed,
FYI...
Adjust dates in lead time scheduling
Determines if and how the basic dates or the dependent requirements dates are adjusted during lead time scheduling, and after scheduling, the new basic dates differ from the old basic dates.
In backward scheduling the system adjusts the basic start date if necessary, in the case of forward scheduling the basic finish date. The basic finish date is not adjusted in planned orders.
the above is from F1 help.
Praveen
Sorry, may be I am wrong...
I have simulated the scenario with the Forward schedule it is working to some extent.
From my observations, I have increased the duration of the activities and again scheduled, the dates are refreshed upto the Project definition level.
But when I reduce the activity duration the dates are refreshed upto the corresponding WBS elements only.....
The same is happening even with the Backward scheduling option too.
Some thing strange.
Praveen
Edited by: b praveen savan on Oct 6, 2010 2:50 PM
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.