Dear All,

We will combine 7 diferent products under Semi-finished goods ( that means we no need shipping box, shipping box lable for 7 mentioned products) into one shipping box and we call the last one is MMR Compo-packs. Theoretically, we have to produce 7 diferent products before we combine them into the last one. However, some of 7 diferent products have been keeping in stock under finished goods (FGs).

That means they used the shipping box & shipping box label already so that we want to unpack these FGs to make the MMR compo-packs and re-used the shipping box & shipping box label for the next production process order.

So, the question like that can we reverse the shipping box & the shipping box label when we convert the FGs to the semi finished goods in system?

Please guide us on the same. Thanks for your help.

Regards,

Maheshaa

Accepted Solutions (1)

Accepted Solutions (1)

madlercm
Active Contributor
0 Kudos

Hi,

If in the process of manufacturing and packing the FG you used a production order to consume both the SFG and the box, you could reverse this process by reversing the confirmations/goods movements in the production order (in the case that the orders are still open). This way you get back in stock your SFGs and boxes, just the way you want.

However, if the production orders are closed already, then you need a new production order (special case) to dismantle the FG into SFG and box.

Regards,

Mario

Former Member
0 Kudos

Thanks Mario,

I have checked the reply today. I will see this & confirm.

Best Regards,

Mahesh