Is it possible to generate aggregated planning (forecast) for product groups in SPP, like we do aggregation at loaction level (using BOD)

Please guide.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Regarding demand aggregation on product group level,SAP recommnedations for APO 7.0-SPP(SAPnote # 1412844)

which states-

-


Simultaneous usage of SCM-APO-SPP and core SCM-APO planning

functionality

It is not intended to use (simultaneously) APO-SPP-DRP and APO-SNP or

APO-SPP-Deployment and APO-Deployment respectively for the same

part/location combination. A simultaneous usage of both will lead to

inconsistent results - due to different planning philosophies and logic

involved.

Forecasting on part location-level

In SCM-APO-SPP the forecast is always and exclusively based on the

combination of part and location. In contrast to APO-DP it is for example

not possible to generate a forecast on an aggregated level, i.e. product

group level, and subsequently to disaggregate the forecast values.

Integration SPP - APO-DP

In an integrated scenario, where SPP is used for forecasting on part /

location level and DP for i.e. (interactive) forecasting on an aggregated

level, separate planning object structures and Infocubes have to be used

and modelled.

-


Further adding to the recommendation,to model generic (non-standard) planning object structures and infocubes with extended use of APO-SPP & APO-DP integrated scenario may lead to chaos in post planning execution (Inventory planning, DRP, Deployment..).