on 10-04-2010 1:31 PM
Hello,
As per standard SAP, Currency displayed in planning board is as per Controlling area currency or not??
If yes then how to display the same currency according to company code currency.
In my case Controlling area currency is GBP & company code is EURO. Right now it is displaying as GBP. I want to display it as EURO.
Thanks in advance
Regards,
Ankush Sethi
Hello,
My Project Currency is EURO only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Yes even i tried with settings in RPP0 but didn't work.
Thanks & Regards,
Ankush
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Again,
Thanks Harsh for your responce.
I have already make the change as "EURO" in OPT7 but still i am getting values in GBP only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In profile for planning board(OPT7), there is option to set currency under general data tab.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.