Hi Team,

I am working in SOLAR01 "Graphic" tab. When i try to connect two business process steps, i am getting the option Sysnchronously & Asychronously. What does it mean? How does it impacts?

Need your guidance on this

Thanks

PSK

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Between the business process steps this means:

Asynchronously - the sender or receiver doesn't expect any confirmation but manual response can be sent.

Synchronously - both transactions communication together, data transfer is together and sender always expects an automatic reply.

Base it on your knowledge of the process and business transactions.