on 10-02-2010 10:02 AM
Hi,
I am trying to upgrade one of the component of ECC EHP Ready system with
SAP-APPL 600 to SAP-APPL 603 and
EA-APPL 600 to EA-APPL 603.
to get the Enterprise Business Activation set OPS_PS_CI_1
I get the Addon conflict error while trying to upgrade using SAINT,
not sure which CRT to be included.
any help.
Regards,
Irfan
Hi,
As per your information, you have EHP4 ready system installed. In order to use this system , you need to upgrade this system to EHP4 level using EHPI installer. Method which you are taking is not supported.
You need to upgrade SAP_APPL and EA-APPL to 604 level then only you can use EHP4 ready system.
Thanks
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.