on 10-01-2010 3:39 PM
Hi Experts,
Can any body help with the following
When trying to u2018closeu2019 a wbs Project at Project Definition level using the LSMW,
If the WBS Project is set to u2018Partial Releaseu2019 the LSMW used to close the project will not work.
However, if the project is set to u2018Releaseu2019 the LSMW will work and close the project.
Can we either closeu2019 projects that are set to Partial Release
Thanks and Regards
Hi Sanjib,
You can set the status to CLSD only if the WBS is either in REL or TECO status.
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That's standard behavior of the system.
As mentioned by, Kabir & Gokul, You can close the project when the system status is either REL or TECO .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You cannot close the WBS/Projects having status as partially released. It should be either REL or TECO.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.