Project plant is different and Plant in PO is different

Former Member
0 Kudos

Hi,

I have a situation in production environment as:

Project is created with plant TG01.

No network/activity is in the project.

Direct PO is made with 'Q'. But the user has put plant in PO as TD01.

GR has been made.

Quality inspection is through.

Project has valuated stock.

Now, how to correct this situation? We need to show consumption of material and correct the plant to TG01 also. or should we change the plant at project to TD01.

Thanks & Regards,

Harsh.

Edited by: Harsh Saxena on Oct 1, 2010 5:24 PM

Accepted Solutions (1)

Accepted Solutions (1)

raghavendra_praveen
Active Contributor
0 Kudos

Hi

You can transfer the project stock from TD01 plant to TG01 plant using 301Q mvt type.

Answers (2)

Answers (2)

Former Member
0 Kudos

Else, you can reverse the GR document, then Cancel the PO.

Create a new PO with correct plant.

Praveen

former_member203108
Active Contributor
0 Kudos

If the material is still in Stock, Why dont you transfer the stock from PO Plant to WBS Plant?