cancel
Showing results for 
Search instead for 
Did you mean: 

PO No range when we ink two SRM system with One ECC system

Former Member
0 Kudos

Hello Experts,

We have a client requirement to link Two SRM Systems with One ECC system.

In this case what number range we need to maintain in both SRM systems for PO.

-The number range of ECC PO should get update whenver the PO is transferred from any of the two SRM system.

-We have Extended classic scenario.

-Also PO Doc type is going to be same.

Can we handle this by increasing the buffer of the number range in one of the SRM system?

Any idea...pls help urgently.

Best Regards,

Anil

Edited by: anil.s.verma on Oct 1, 2010 4:33 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

laurent_burtaire
Active Contributor
0 Kudos

Hello Anil,

Being in Extended Classic Scenario (leading PO being in SRM, R/3 PO number range is concidered as external because PO number is given by SRM), the only solution for you is to:

1- give same number range interval for PO (internal in SRM system 1 and SRM system 2, external number range in R/3), e.g. 3100000000 - 3199999999

2- in SRM system 2, fill in current number with (for example) 3159999999 and let empty (or current value) in SRM system 1

3- assign, in each system for your concerned transaction type, number range as internal in SRM and external in R/3.

In this way, you will avoid overlaping in R/3 between PO numbers coming from SRM system 1 and SRM system 2

Regards.

Laurent.