When i create a planned order in APO i have to operations that follow each other perefctly when rescheduling.
When i look at the relationships they have a start-start relationship.
When i convert this planned order to a production order, the successor operation does follow the predecessor operation only when i move the order forward in time. So if i move the main operation backwards in time the other stays unfixed.
Does anyone have any idea what to do to avoid this. When i look at the relationships, there was automatically created an additional end-end relationship for these to operations.
Kind regards,
Bert
Hi Bert,
In the master recipe if two operations exists 10 & 20 with phases 11 & 21 with respective relationship start - start.
You can achieve the result (phase 21 should be scheduled forward or backward whenever the phase 11 is rescheduled) by maintaining the maximum offset time between the phase relationship as 1 sec/min in ECC system.
CIF the PPM/PDS and then create the planned order or production order and check by rescheduling.
Regards
Sravan maturu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bert,
Have you explored the options for the "dependent objects" in the strategy profile.
Thanks,
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.