Change in delivery quantity for batch managed items.

Former Member
0 Kudos

30.09.2010

Hi friends,

We have activated batch management. During delivery after the batch is determined and if i want to change the delivery quantity say for example from 50 to 30 then first i have to go and adjust the quantity in the batches to toal 30 and then come back and change the delivery quantity from 50 to 30.

After searching the forum i have found user exits, but other than the user exits is there a standard configuration wheren if i change the delivery quantity the quantity is adjusted in the batches. Please advise.

Regards,

Udaynath.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

As per SAP this is a standard behaviour.

Former Member
0 Kudos

07.10.2010

Friends, has anyone carried out changes to suit clients requirements. Please advise.

Regards,

Udaynath.

Former Member
0 Kudos

Udaynath

Did you try working with the batch strategy config?

Try working with fields a) Over Del allowed, and b) Qty proposal.

Path: SPRO/IMG/Logistics - General/Batch Management/Batch Determination and Batch Check/Strategy Types/Define Sales and Distribution Strategy Types

Hope this helps. Let me know.