VSEVFG_CN (Version: PS EV, percent of completion)

former_member214674
Contributor
0 Kudos

Hi,

I am creating project versions in CNE5 but system is not updating version table VSEVFG_CN. Please suggest if there is any setting needs to be done to update the same table or is there any other table that gets updated for project version(progress data)

Thanks & Regards,

Abhinay Gautam

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member214674
Contributor
0 Kudos

VSRPSCO_CN

Former Member
0 Kudos

Hi,

Version Details of Project definition gets saved in VSPROJ_CN table.

Version Details of WBSE gets saved in VSPRPS_CN table.

Basically VS<table name>_CN is 'Version Master Data'

Regards,

Harsh.

former_member214674
Contributor
0 Kudos

Thanks Harsh.

But I think table VSPROJ_CN, VSPRPS_CN does not give any progress related data(Plan POC and Actual POC). Let me know if i misunderstood.

Any other suggestions please ?

Thanks & Regards,

Abhinay

Former Member
0 Kudos

Hi,

EVGEW is the field for POC in VSPRPS_CN.

Regards,

Harsh.

former_member214674
Contributor
0 Kudos

Hello Harsh,

EVGEW is POC weight, whereas my requirement is to capture Plan and Actual POC.

Folks, Any inputs ?

Cheers !!

Abhinay

Former Member
0 Kudos

Hi,

It is Plan value itself.

Actual POC i guess is not stored in any table, it is determined at runtime.

Regards,

Harsh.

former_member214674
Contributor
0 Kudos

Hello there,

Plan POC is different from POC weightage. Plan and Actual POC gets stored in table RPSQT.

In our scenario, I have created a project version in CNE5 and want to know in which table, does system store this version Values(Plan POC, Actual POC, etc.)?

Regards,

Abhinay