on 09-29-2010 12:15 PM
Hi Experts,
When doing a Good Receipt Purchase I can see the network of the item but the WBS field is always empty. How does it works? It's possible to fill this field with the wbs information?
Thanks
Hi
If you are using network costing (network - acitvities and material components) then what ever the PRs getting generated from material component they will have account assignment as Network (AAC being N or P depending on customization choice). When you use Easy cost planning and your planned materials generate PR then they will have WBS element as account assignment. You cannot have both WBS element and network as account assignments as those two are true account assignments.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
WBS element, networks are ture account assignments means they carry costs like cost center and internal orders. You cannot have two account assignments for one document (accounting posting happens for this document) unless one of them being statistical account assignment.
If you are using network costing, you have a choice of generating PR either on network or WBS element but not on both. If you want to fill WBS element in MIGO then use separate field to fill it using enhancement. But do not fill WBS element in account assignment field unless your WBS element is ticked as statistical.
Thanks Praveen Raghavendra,
If you are using network costing, you have a choice of generating PR either on network or WBS element but not on both.
How I choose between generating the PR on a WBS element (instead of doing it on a network). And, sorry if I've misunderstood your explanation, but as you have told I understand there is not a big difference between both options as both will carry costs like cost center and internal orders?
Thanks again
If the Acct assignment category is N then it will have network information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I like how it works the process with Item Category "N" (Automatic Purchase Requisition creation, ...) but I would like to have the material linked with the WBS element.
And I have no "P" item category, excuse my ignorance but where I should make the account assignment P that you are telling me?
Thanks
In absence of networks if we want to create PR manually for a WBSE then we have option of a/c assignment P & Q. If you want PR generation automatically on networks then it is not helpful.
With a/c assignment you cant get WBS element as "N" means a/c assignment to network not WBSE.
Edited by: Kuldeep Bidalia on Sep 30, 2010 2:57 PM
If the Acct assignment category is N then it will have network information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.