Did you mean: 

Sales Order cost estimate with variant config

Former Member
0 Kudos

Hi

I'm hoping for some advice on costing on a variant material.

I have created a sales order for a variant material and ran a cost estimate to get costs for the sales order. Should this populate a cost condition within the sales order pricing? How can the margin be seen in the sales order?

Thanks for your help.

Ashley Shannon

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Ashley

Yes, if you have done your settings correctly, especially Requirements class set up (see the documentation link), then the cost estimate will flow to a condition type in Pricing, usually EK01/EK02 conditions. These conditions are used to calculate sales prices (PR00) in cost-plus (mark-up) scenarios.

Link: http://help.sap.com/erp2005_ehp_04/helpdata/EN/90/ba6da4446711d189420000e829fbbd/frameset.htm

However Profit margin as calculated in a sales order comes from VPRS condition (which is based in Material Master) and is the difference of net value and VPRS condition value in normal circumstance.

Hope other more knowledgeable experts will weigh in.

Former Member
0 Kudos

Thank you Chandrasekhar.

Your answer is a great help to me and has confirmed what I thought to be correct.

Best regards

Ashley