Hi,

I've a question about sampling drawing procedures. Is it possible to have different sample drawing procedures per operation. I've an inspection plan with the following settings:

- Insp points 200 (inspection points for physical samples)

- Sampling drawing proc YP-04 (number of samples = number of containers)

But what i want is that only a few master inspection characteristics or operations (mainly microbiological) are dependent on the number of containers. And for the other analysis i only want to perform one test.

Is this possible? Because now all operations and analysis are dependent on the number of containers.

Thanks for your help.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Well once you define the Number of container in the sampling drawing procedure & define this SDP in the task list header ,Its applicable to all operations & MIC of that task list

maarten_muetgeert2
Participant
0 Kudos

Is there no other way to realize something similar?