Automatic Creation of Planned Order in PPDS Horizon

Dear Experts,

Kindly answer my following query.

I have created PIRs before/inside my PPDS Horizon (its also falling outside horizon as SNP horizon is shorter than PPDS Horizon). If I check the PIRs created by me in /SNPAPO/RRP3, it also shows me planned orders corresponding to them. However, if I create PIR outside PPDS horizon then system is not automatically creating the planned order.

Kindly let me know which master data/configuration setting is responsible for automatic creation of planned orders within PPDS horizon.

Best Regards

Rinju

Edited by: Rinju Mukherjee on Sep 26, 2010 10:05 AM

Former Member
Former Member replied

Dear Rinju,

Check in Product Master PPDS view the Planning procedure maintained? if it is balnk check in the heuristic, the palnning procedure maintained.

Since automatic planning procedure(3) is maintained, that is the reason it is creating order proposals, it self.

Sree