on 09-24-2010 10:50 PM
Hi,
Does anyone know how to configure evaluations at level task only for released projects?
What we need is that the evaluation will be executed only when project has released status. Is that possible?
Thanks a lot,
CAMILO URIBE
Hi CAMILO,
After the notes 1422722 & 1465106 is a service method available, which allow the customer to dis-able the evaluation.
CL_EVE_EXTRACT_FACTORY SET_ACTIVE
You can put a codes in some BADI method, which is called during save. Within the Badi-Implementation, call the SET_ACTIVE method, so that the evaluation not be tiggered (until the project get released.)
KInd regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Problem solved by Note 1321224 - DPR_EVE_BATCH_DPO and unexpected alert mails.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.