Refresh problem in Shopping Cart and PO in cost distribution in SRM 7.0

Former Member
0 Kudos

Hi ,

As of now we are working in SRM 7.0. Actually when we are changing the account assignment cateogary from WBS to Asset then the cost distribution need to be changed from Percentage to quantity and vice-versa. But this is not happening .

Can somebody hlp on this if you guys came across such issue.

Regards,

Kalyani

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Kalyani

Cost distribution will not change automatically when you change the account assignment category. You will ve to distribute it manually on the same lines as you did for Cost Center earlier

Regards

VIrender Singh

Former Member
0 Kudos

Hi,

Thanks. This issue got fixed through my custom code.

Regards,

Kalyani Dadi

Former Member
0 Kudos

I don't think it is the standard functionality to change the cost distribution when you select a different account assignment category from the drop down. Have you had this feature in your earlier SRM releases?