CJV4 : Transfer for simulation to oper.proj leads to termination

Former Member
0 Kudos

Hi All,

While executing the CJV4: Transfer of project from Simulation version to Operative project, program getting terminated :

The following way I came across the problem:

Created a project with one Network Order and scheduled:

ProjDef: C-1001------Operative Project

L1 WBS: C-1001

L2 WBS:C-1001-01

NW:400001

Act:400001 0010

Act:400001 0020

L2 WBS:C-1001-02

I would like have some changes to the project, so transfer the Operative Project to Simulation through CJV4, and added one more network order to simulation project in CJV2 and scheduled.

ProjDef:C-1001 -


Simulation Version, (SIM1)

L1 WBS:C-1001

L2 WBS:C-1001-01

NW:400001

Act:400001 0010

Act:400001 0020

L2 WBS:C-1001-02

NW:400002

Act:400002 0010

Now I would like transfer from simulation version (SIM1) to Operative project through CJV4, getting the following error:

"Activity/activity element 0010 already exists

Message no. CN876"

"Activity does not exist in network

Message no. CN812"

"Termination: Too many errors (more than 10% of methods)

Message no. CJ280"

If anyone had face the same kind of situation, pl. advise me how resolve the Issue.

Vemula

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

answered

Former Member
0 Kudos

Issue has been resolved with the following SAP Note:

"Note 1401303 - CJV4-> Error CN 876 while transferring a simulation version."

Vemula