on 09-24-2010 10:29 AM
Hi All,
While executing the CJV4: Transfer of project from Simulation version to Operative project, program getting terminated :
The following way I came across the problem:
Created a project with one Network Order and scheduled:
ProjDef: C-1001------Operative Project
L1 WBS: C-1001
L2 WBS:C-1001-01
NW:400001
Act:400001 0010
Act:400001 0020
L2 WBS:C-1001-02
I would like have some changes to the project, so transfer the Operative Project to Simulation through CJV4, and added one more network order to simulation project in CJV2 and scheduled.
ProjDef:C-1001 -
Simulation Version, (SIM1)
L1 WBS:C-1001
L2 WBS:C-1001-01
NW:400001
Act:400001 0010
Act:400001 0020
L2 WBS:C-1001-02
NW:400002
Act:400002 0010
Now I would like transfer from simulation version (SIM1) to Operative project through CJV4, getting the following error:
"Activity/activity element 0010 already exists
Message no. CN876"
"Activity does not exist in network
Message no. CN812"
"Termination: Too many errors (more than 10% of methods)
Message no. CJ280"
If anyone had face the same kind of situation, pl. advise me how resolve the Issue.
Vemula
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Issue has been resolved with the following SAP Note:
"Note 1401303 - CJV4-> Error CN 876 while transferring a simulation version."
Vemula
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.