on 07-14-2006 3:23 PM
Hi,
I am working on SRM Extended classic scenario.
Front end BBPCRM 4.0 SAPKU40007
Back end 4.6C SAPKH46C47
I have a material A which has the base unit of measurement Package and this material exists in many of the plant so whenever I order this material it is ordered in Packages. Also I have maintained alternative unit of measurement Pieces and it is as follows
1 pack = 1 pack
1000 piece = 1 pack
But now for one plant I have to order this material in pieces then how can I be able to do so?
Is this can be solved by Catlog content management
Please assist me..
Regards,
Raj
Hi
You may use the order unit, variable order units fields in R3 material master in the purchsing data view.
So at the time of creation of PO you can select the respective purchase order unit for the plant combination.
Regards
Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.