Hi,
I have 2 questions related to subprojects:
1. Is it possible plan cost of a subprojects can be display or uploaded to the main project? ( cprojects)
2. Is it possible plan cost of a subproject can be upload to the item ( when item is related to the main project)?
Thanks a lot,
Sara
Hi Sara,
Regarding your Quest no 1.
The Link between the task of master project & subproject is limited to dates & alerts on date changes, deletion of master / subproject & deletion of interlink between task & subproject.
The task of the master project behaves like a normal task. The subprojects are costed seperately. the costs of subprojects are not displayed in the Master project.
If you want to display the cost in master project, plan the hours & cost rate in the master task & dont carry out cost planning in the subproject, keep the cost rate as 0. This is just a workaround.
Regards
Sejo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
6 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.