Credit check againest Next review date

Former Member
0 Kudos

Hi All,

Could you please help me the check againest the Next review date.

In my business Next review date is not maintained in the Credit master, and in OVA8 we have activated the next review dateand the status should be block?

We have maintain the buffer days as 30.

So how the system will check the next review date? If the Next review date is not exists in the credit master then which date system will take into consideration to check the date?

Kindly help...

Regards,

SK

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi!

In case you do not maintain the review date in Credit Master, then system shall react as per the 'system reaction' in auto credit control.

Regards

Arun

ajitsingh6
Active Contributor
0 Kudos

Dear Friend,

It will consider your Document date as Base date and will add the Buffer day to that.

For exp. If Document date is 01.08.10 and buffer day is 30 days then Next review date is 30.08.10. If Next Int. date is

available in then it add on those date as well.

Regards

AJIT K SINGH

Former Member
0 Kudos

Hi Ajit,

Thanks for the reply. Document dae means Order creation date?

Regards,

SK

Former Member
0 Kudos

Yes, Sales order Creation date.

Regards,

Raghav

Shiva_Ram
Active Contributor
0 Kudos

The document date is normally delivery date.

For further info check the link, http://help.sap.com/saphelp_45B/helpdata/en/e5/0783804acd11d182b90000e829fbfe/frameset.htm

Regards,

Former Member
0 Kudos

Hi Sivaram,

Could you pls explain if the system take it as Delivery date as Document date then againest which date system will check the next review date?

Regards,

SK