Hi experts,

We need to determine when BOP finishes and change its status to 'Update ended(X)'. We have to trigger an event when the status change to 'X'. Do you know any user-exit for this?

Thanks a lot.

Regards,

Nene

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

We are trying to implement the same, and at the moment tought of developing a custom program , which retrieves the BOP status from table /SAPAPO/BOPHEAD and if status is 'X' we are raising an event which triggers next step of my job.

If BOP sttaus is 'U' check for TQA count, if TQA count is Zero check for RFC queues......if any failed queues...giving that error message and continuing next job.

We are not using any user exits.

Hope this gives atleast an idea. Share with us , if you find any best approach.

Regards,

Deepthi