HI,
We are using Time continuous planning in CTM. In our scenario the resource definition has both break duration and utlisation needs to be defined less than 100%.
When we are trying to maintain this data in the resource CTM master data consistency check is showing inconsistency.
How can I define break duration and utilisation in resource and use it for time continuous planning in CTM.
Thanks & Regards,
Sanjog
Hi,
When you carryout time-continuous planning in CTM, following points to be considered.
Rate of resource utilization and break duration( Utilization to be 100% and no break to be maintained.
For single-activity resources, multi-activity resources, and calendar resources, or for the available time-continuous
capacity of mixed resources, always enter a rate of resource utilization of 100 % and a break duration of 00:00:00.
Otherwise, the SAP liveCache determines a different duration than CTM planning does for the corresponding
activities. This may cause the system to fulfill the demand too late.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.