on 09-22-2010 5:52 PM
We have gotten to a point where we need mantenance plans to come due on a certain date annually, but have a 120 day lead float time. Is there a way that I can have a maintenance plan go to a specific date instead of a number of days, etc?
Hi
Which ever maintenance plan you are using whether single cycle or Strategy, Use Scheduling Indicator as TIME-KEY instead of Time or Factory calender. This will serve your query.
Example
Time-based maintenance plans
You schedule a preventive maintenance plan with a strategy containing a monthly package (for scheduling purposes a month is taken to be 30 days):
Time
Current date: 04/10/1995
Next planned date: 03/11/1995 -> current date + 30 days
Key date
Current date: 04/10/1995
Next planned date: 04/11/1995 -> on the 4th day of each month
Factory calendar
Current date: 04/10/1995
Next planned date: 16/11/1995 -> current date (or next workday)
+ 30 workdays
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi jeremy wieland,
you can have maintenance plan go to a specific date by using single cycle maintenance plan.in single cycle plan go to schedule indicator and select the time key date button & save it.Then execute the maintenace plan.
Regards,
Bharat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
you can use single cycle plan and specify under the scheduling indicator select the radio button of time-key date. then u can get the maintenance plan on the specific date.
i think this will help you
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.