Good Issue date in the Sales order should 1 day difference from the MBDAT

former_member372321
Participant
0 Kudos

For the particular customer, i want to have difference of 1 day in between the material availability date & good issue date in the schedule line. As per standard i can't made any changes in route and shipping point. Suppose material availability date in sales order is 22.09.2010 than my good issue date should be 23.09.2010 in the sales order. Any body having any idea how can we handle this case and what are things we need consider impact of this change.

Regards,

Srinivas.

Accepted Solutions (1)

Accepted Solutions (1)

former_member183879
Active Contributor
0 Kudos

Hi,

I think you can easily enable this in Route scheduling /Delivery scheduling. You have to maintain the load time and pick/pack time as the total of 8hours. If this is done, then after material availability date, one more day will be added and the final day will be considered as GI date.

If you dont want to do this, you only have to enable this by Z by using a user exit where you can add one day to the MBDAT and update that in GI date.