on 09-21-2010 6:03 PM
Hello,
How can I set up a job in production with the following details:
Job runs from Mon-Fri only between 2:05 pm - 2:05am (next day) with interval of every 2 hours.
Thanks.
what job you want to schedule.
are these DBA actions job. usually data back up and log backup jobs are scheduled 2 hourly
Regards,
Surpreet Bal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Create 5 jobs, one per day and define start date, time and end date, time and periodic for two hours from time you start and doesn't run after 2.05 a.m. on 2nd day.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |