on 09-21-2010 2:45 PM
How do I check to see if priority 2 is set to use a calendar or it is using business days to calculate the start and end dates?
Thanks,
Annette
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ususally, the system will take Factory Calendar into consideration if you select the day as unit (start and end date units), where as for other units -e.g. hours non working hours are not consedered.
You can check your priority type config settings in qm - quality notification - notification processing - response control - define priorities.
Hope it helps.
Thanks,
Ram