We are using work force planning to assign resources to activities. We have some problem with one of the work centres. When we click on the person dropdown box in the personal assignment tab then we would expect to see the individuals that are in the work centre associated with the activity. We can see six persons from project builder and when we checked work center master data we could see only four persons.
When checked thoroughly, the data at work centre master data is picked from HRP1001 and its showing only 4 persons. At the project level, the data is picked from the same table but initially fetches with work centre as input and then capacity ID as input. Finally it combines the data (6 Persons) and show from CJ20n and its different from the work centre data.
is this the standard behavior or we missing something
Regards,
Laxminarsimha
I think you have assigned two person at capacity category level for that WC.
Open your WC in CJR3 --> Click on capacity header icon -->on new screen click on HRMS link button ( check no of person assigned here it should be two )
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.