on 09-21-2010 5:16 AM
Hi experts,
Can i split a production order in many others in order to balance the resources?
Can i use any heuristic or the optimizer?
thanks in advanced
Ivan
PP/DS planning does not have an order split functionality based on scheduling. if you have fixed operations and 2 slots of 1 h you cannot schedule a 2 h operation. The APO scheduler will not split the order or operation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use the PPDS Optimizer to balance the resource before the Process Orders are created.
Order split functionality exists only in R3 system
Thanks,
nandha
Edited by: S.Nandakumar on Sep 24, 2010 6:11 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.