Hi QM experts,

My client needs to configure DMR for skip inspection lot.

Scenario Requires following steps:

1. Maintain PPAP approved status

2. After PPAP approval inspection of next 10 consecutive lots.

3. If all lots OK, system skip 1 in 2 lots.

4. Then system again checks next 6 consecutive lots, if there is any rejection again repeat step 2 else skip 1 in 3 lots.

5. Same cycle will repeat for skip 1 in 5, then skip 1 in 10, skip 1 in 20 and so onu2026

I am new to PPAP status and DMR. Kindly guide how to map this in SAP. What are the SPRO settings required and what master data to maintain for it, and what will be the process flow.

Regards,

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

in need of experts Advice and Guidance.

Regards,