Stock and SNP, PP/DS restrict

Former Member
0 Kudos

Dear colleague,

Can somebody suggest a way where.

1. I need to restrict the stock for planning by SNP and PP/DS after it has been produced for 3 months and after 3 months it should automatically be in use.

Thanks

Sandeep

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sandeep,

Few possibilities are

1) Try maintaining maturation time in material master to 3 months

so that during that period, system will not plan the stocks

2) Try using suitable movement types in R/3 system to keep the

stocks under restricted area so that it will not get reflected in

APO and available during planning. Once in 3 months cycle, all

such stocks are to be released to APO through mass job for

planning

Regards

R. Senthil Mareeswaran.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check for the Shelflife functionality which PPDS honours but SNP in a restricted way.

395321 Note for reference.

579556

Thanks,

nandha