on 09-20-2010 12:42 PM
Dear experts
This question is probably best suited for the QM forum but I will still ask...
We are using Handling Unit management for our raw material store. All raw materials are active for Inspection via UD.
The usual GR process is > Create Inbound Delivery > Complete Packing in Delivery > Post GR > Putaway.
The inspection lots are created after Goods Receipt is posted.
Is it possible to Display/Print the Physical Sample quantities for the inbound delivery materials before packing or GR?
Many Thanks
Abdul
Hi Abdul,
Looking to your question - I felt , you could Guide Me.
Scenario :- 1
For HU Managed Raw Material , If we activate inspection type 01 , and in the parameters if I activate check Box of HU Management.
The follwoing process happens.
1. At MIGO - Inbound Delivery is created
2. And as we do GR against that Delivery - Inspection Lot gets generated.
But Here we have to do result recording / UD against HU.
Which Seems to be OK process.
Scenario :- 2
If we do not activate HU Management in inspection type 01.
Then My understanding is that we have to do RR / UD against the Material.
But In my case here - No Inspection lot is getting generated.At GR it shows that Material of the stock type Q.
For which we use VLMOVE. We see nothing in QA32.We do not do any RR/ UD.
Kindly guide me ... if I have to do any necessary config for the same.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.