CNS0 - Material not picked from Project

Former Member
0 Kudos

Hi All,

I am trying to complete delivery from project. I did the following steps:

1. Created a material component in the Project to a network activity and raise a reservation / requirement.

2. MB1C - did a GR for the component to project stock (Movement Type 501Q)

3. MB1A - issued stock to project network activity from project stock (Movement Type 281Q) - delivered "To Reservation..." - tried with and without reservation.

4. Went to CNS0 and entered the project number and clicked on Components.

For some reason, the material is not picked here. When I just enter the quantity to check, it says "Material quantity does not exist". Could you please help me in the right direction to resolve the issue?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

Yes, you wont find any material to be delivered, because you have already consumed the material in your step 3.

Dont do step3. and do step4 after step 2.

Also, look in SAP Help and read about CNS0.

Former Member
0 Kudos

Thanks Ahmed,

I tried not issuing to the network activity, but it still doesn't pick the material in CNS0. However, it shows available project stock against my project WBS element in MMBE. I will read the help documentation, but are there any more pointers you could throw?

former_member203108
Active Contributor
0 Kudos

I will read the help documentation

Read SAP Help and check what you have done with the constraints listed out in SAP Help. This will give you more pointers.