Hi All,
I am trying to complete delivery from project. I did the following steps:
1. Created a material component in the Project to a network activity and raise a reservation / requirement.
2. MB1C - did a GR for the component to project stock (Movement Type 501Q)
3. MB1A - issued stock to project network activity from project stock (Movement Type 281Q) - delivered "To Reservation..." - tried with and without reservation.
4. Went to CNS0 and entered the project number and clicked on Components.
For some reason, the material is not picked here. When I just enter the quantity to check, it says "Material quantity does not exist". Could you please help me in the right direction to resolve the issue?
Yes, you wont find any material to be delivered, because you have already consumed the material in your step 3.
Dont do step3. and do step4 after step 2.
Also, look in SAP Help and read about CNS0.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.