Dear All,
I have a scenario where i can produce One material on six resources. But I have constraint that i have only three dies which can be used on any resource to produce the material. Now if i run optimizer without considering the constraint (Die) then optimizer can create planned order on all these six resources. But if optimizer considers the Die as a constraint then it will create planned order on any three resources. I have created Six resources in APO as multimixed resoureces. For Die i have not defined any resources.
My query is how can i map the Die(Constraint) in SNP Optimizer such that i get the planned order only on three resources.
Regards
Sunil
Hi,
Your Die is more like a PRT (Production Resource Tool) , and not a resource.
PRT scheduling and capacity planning is little different scenario and not fully supported in APO ( to my understanding).
Regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.