on 09-16-2010 11:38 AM
Hi,
While creating a sales order on a holiday date (Sunday),it shows a delivery date on the next possible date (i.e) on Monday.But if i change the delivery date on Sunday the system is accepting and I'm able to proceed.My requirement is I'm need to block the sales order if i try it on holiday dates.
I have already setup the factory calendar in plant,customer master data(sales area data).This is for your information.
Thanks in Advance
Regards
Palanivel Rajan
Edited by: sapsd-palanivel on Sep 16, 2010 12:38 PM
Dear,
Please check your Factory Calender for following,
1)Factory calendar set into Plant
2)Factory calendar set into Shipping Point ( Have u assigned it to shipping point also)
3)Factory calendar set into Customer Master for an Unloading Point.
Regards
AJIT K SINGH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You need to check the calendar assigned to the shipping point. Please check if Sunday is a working day.
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.