on 09-15-2010 12:32 PM
Hi All,
In Resources we need to define the shift factor Definition. Where should we maintain the values...in Easyaccess or SPRO ?
We use Mulit mixed resources.
Thanks in advance
Durai
Hi,
If I understand your requirement correctly: Go to resource master, select your resource and go to capacity variants tab,
Thanks,
Satyajit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can maintain your PPM as per your requirement. Say you have PPM which will give 100 PC output product per Hour. Now You can maintain capacity of the resource (Resource attached to this PPM) accordingly. Like 1st week 8 HRs per day. 2nd week 9hrs/day, 3rd week 10hrs/day....
Now you have 56 working HRs in the 1st week, 63 HRs in the 2nd week and 70 Hrs in the 3rd week. So, your PPM can produce 5600, 6300,and 7000 PCs for those three weeks respectively. (your production calendar is 7 days in a week in this case).
Hope this helps.
Thanks,
Satyajit
Hi Satjyajit,
Thanks again.
The problem is what we are suggesting is increase in number of hours per week.
But what the user is asking is increase in ouput for the same shift period (say 8hrs)
ie., 1000 pcs in 1st week - 8 hrs
1250 pcs in 2nd week - same 8hrs
1500 pcs in 3rd week - same 8hrs
Your suggestion for this.
Regards
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.