How can i attach a document to a specific material revision level ?

Former Member
0 Kudos

Dear guru.

I manage a material with revision level.

I need to attach a specific document , created using DMS , for every revision level of this material.

How can I do that ?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Cris,

This cannot be achieved through std process.

Alternate way is, As soon as you create material with different revisions better to create document with material no as document no with different versions.

In SPRO->Document Management->Define document types->Define Object links,for object MARA set document version as 1:Default:current version ,so that whenever you view material in MM02/MM03 of different version you can see document with current version only.

Regards

Bhanu

Answers (2)

Answers (2)

Former Member
0 Kudos

....or maybe you can study the Engineering Change Management for this functionality ?

Former Member
0 Kudos

Hi Crisato,

The solution for your query is if you have revisions of same material no. then it's not possible. but if material no. is different then it's possible.

Now, further you can ask abap'r to write a programe for same material no. and maintaining revision levels.

In standard it's not possible. With z-development it's possible.

Hope this will help.

Regards,

Ravindra