Caledar is not being taken after importing a file from Msproject

Former Member
0 Kudos

Hi,

We are workin with MsProject-cProjects integration and all configuration were made taking into account the SAP recomendations; but, the problem we are having right now is with the calendar. The calendar in Msproject is "Colombia" (Which was downloaded from cProjects) and after Uploading a file, the calendar in cProjects is "International".

We have debugged the integration and have noticed that calendar is read as "International " before doing the integration.

Does anyone knows if is something missing?

Thanks a lot,

CAMILO URIBE

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Problem solved by customizing

former_member201206
Active Contributor
0 Kudos

Hi CAMILO URIBE,

As far as I understood, the import does not take the calendar from MSproject, rather take a fixed one. The background is that, the MSproject using numric for calendar and the cProject uses characters. During the export, an automatic numric calendar ID is created for MsProject, but the mapping between Msproject and cProject calendar does not exit, so that the later importing action will ignore the Msproject calendar ID.

Search SAP notes in this topic should give more details.