Hi Experts,
The assembly processing runs, but I want to create a complexe WBS Structure and only one global network.
When I generate automatically the project from the sales order, only one WBS Element and one Network are created, despite of a complexe structure in the standard project.
If I affect activities under each standards WBS, the complete structure appears but I must delete each activities deleted for save the desired project structure.
Exist there a solution to generate on network without activities, and a complexe project structure ?
The question 1162886 don't solved my problem and the "only one root" is not ticked on OPSA.
Thanks a lot for you help
herieric
If I affect activities under each standards WBS
What do you mean by "affect activities"?
The question 1162886 don't solved my problem
- what does the number refer to? is it a note?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ok, I miss took the number as an SAP note.
Its good to see that you have searched the forum before creating the thread. Please do so in future also.
I dont think your requirement shall be fulfilled in Std. SAP. Because, the job of the assembly processing is to create an "Order" (in our case, network) from the sales order not WBSE or Project Definition. So the system will care about only the network & activities and other objects to which these activities are assigned. The system creates WBSE & Project Definition because the std. network is assigned to Std. Project. If the network / activities are not assigned to any std. WBSE then that particular WBSE will not be created.
If you want the entire project structure to be created then you should use activities and assign the activities to the WBSE, no other option.
May be you can look for some kind of development which shall delete the activities automatically during save of the project after it is been created by sales order.
Edited by: Ahmed Rifaee on Sep 14, 2010 9:53 PM
As told by Ahmed, This is not posbile as of now. This is one of the common requirement for Professional service Industry which use WBS only for the purpose of cost tracking and not any logistic cycle. So, ther dont required network at all. SAP is working on this solution most probably it will be in EPH5. Till that time development is only solution.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If I understood correctly. He don't wanted to assign Network activity to std. WBS element in template because by assigning he is able to created requied WBS structure but system is also creating network actiivty of template as well.
If he is not assiging std. netwrok activity to std. WBS than he is not able to create all required WBS.
Herieric: Just check after maintaining higher level std. WBS in your STD. network whether it creates requried WBS structure when in your std. nettwok you have not maintaiend link between network activity and std. WBS.
With Regards
Nitin P.
For assembly processing to work network has to be there - the link between the sales order and the PS object for logistics side resides in the network header (apart from the costing link on the billing WBS element)
Will need to check if you can create a standard network template without any activities, but if so I do not still see the problem
Nitin, I dont think it will work, because the purpose of assembly processing is to create network. So when the operative network is getting created from std. network, system will create only those WBS which has some relation to this pertaining network.
Even for example , following is my Std. WBS:-
WBS 001
WBS 001.1
WBS 001.2
WBS 001.2.1
Suppose if I assign a Std. network to WBS 001.2.1 and no assignment made between Std. Network to other Std WBSE, The system will create following operative structure:-
WBS 001
WBS 001.2
WBS 001.2.1
It wont include WBS 001.1 in operative structure, because it has no relation with Std, NEtwork.
That's what I am saying by giving level 1 WBS and check. Refening to your example
Suppose if I assign a Std. network to WBS 001 and no assignment made between Std. Network to other Std WBSE, The system will create following operative structure:-
WBS 001
WBS 001.1
WBS 001.2
WBS 001.2.1
By giving level 1 WBS he need not to create unwanted network activity and assign there Std. WBS Element. As he dont intended to user that network activity in his operative structure.
With Regards
Nitin P.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.