on 09-14-2010 12:49 PM
Dear Experts,
I have Defined Project Coding Mask as PrjID "U" and coding mask /0000.XX-00 and created one project profile.
I have copied the transport request from 200 client to 220 client by SCC1.
When in 220 client transaction CJ20N operated at the same moment I got the message as "Entry length is incorrect. "U/0000.XX-00".
The details of message is
________________________________________________________________________________________________
Entry length is incorrect. "U/0000.XX-00"
Message no. CJ610
Diagnosis
The key that you entered for the project definition or the WBS element does not have the same length as was entered in the coding.
System response
Processing stopped.
Procedure
Enter the key as it was defined in the coding of the project definition or WBS element: "U/0000.XX-00".
Procedures for the system administrator:
Check whether the coding for the project definition or the WBS element were properly maintained on the screen. Make any necessary changes.
____________________________________________________________________________________________________
But I am not getting the above error in 200 Client and only getting error after copying the transport request in 220 client.
Kindly suggest the solution.
Regards,
TusharA
Hi,
Check OPSK in both clients.
Regards,
Harsh.
Edited by: Harsh Saxena on Sep 14, 2010 6:07 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When are you getting this?..at the time of creating project with this coding mask...or during copy ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ok, I thought it is after saving project with the project coding mask.
Because, in my earlier project one of my user got similar kind of problem in production system after we gone live. The mistake he did was instead of creating U/0001 as project code he entered U/OOO1 i.e., he used capital 'O' instead of 'zero'. You wont find much difference between these two letters but only a small dot. I thought you are also experiencing the same problem.
Hallo Praveen,
In CJ01, no such error occurred and proj definition U/0000.XX.01 is accepting.
I am unable to go in change or display mode for project builder, before that system stops processing and ask for Exist from th transaction.
How I can set the initial options for Project Builder transaction.
Regards,
Tushar
I think, your user has set "Preview last project" option in CJ20N user settings and whenever you try execute CJ20N it try to load the past project, and unfortunately there are some inconsistencies exits for that project.
Enter the CJ20N in debugging mode and check which project it try to load and open that project in some other user log in and see.
Check whether your transport request is copied to 220 client successfully or not?
Also in 220 client check, whether the new code 'U' exists or not after the copying of TR from 200 to 220..
Revert with your feed back.
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.