Hi,
when i executed the commitments(POS), if the expenditure exceeds the budget, system should throw the message and it should send the email to the person responsilbe. In this scenario iam using the option "warning with mail to a person " in the Tolerance limits. my question is person resposible field in the project builder screen is just a text field. How system will validate this , If iam wrong please guide me the process in this scenario.
John
You will assign login id to the person responsible. that is how it will triger the email
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Person responsible are defined in the IMG, using transaction OPS6, there is a field Office user against the person responsible.
Check is there any SAP login user id is maintained, if not you can mention a valid SAP user id for the person responsible.
System will then trigger a mail to the SAP user in SAP Business Work Place. That user can check the mail using transaction SBWP.
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.